Design and Construction Program Notes

by
David W. Lloyd, P. E.
Chief, Design and Construction Program

STATUS OF DISTRICT DESIGN PROJECTS

Project Participating Jurisdiction(s) Status
Marston Lake N./Bear Cr. Park Denver Complete
Ralston/Leyden Feasibility Arvada, Corps of Engineers On hold
Van Bibber Final Design Arvada, Corps of Engineers Complete
Little Dry Creek Phase C Westminster Complete
Little Dry Creek RR Crossings Adams County Complete
Massey Draw at Carr St. Jefferson County Complete
Jewell Wetland Detention Aurora Complete
Grange Hall Creek Northglenn 80% Complete
Lakewood Gulch - Perry St. Denver 10% Complete
Niver Creek Tributary L Thornton 30% Complete
Drainageway E Columbine Valley 95% Complete
Irondale 80th Ave. Outfall Adams County, Commerce City 95% Complete
Littles Creek Arapahoe County 25% Complete
Goose Creek Phase 3 Boulder 25% Complete
McKay Outfall Adams County 50% Complete
Pleasant View Trib. to Lena Jefferson County 95% Complete
Rangeview Gulch Littleton 90% Complete
Cottonwood Creek Arapahoe County 40% Complete
Westerly Cr. @ Expo Park Aurora 40% Complete
Lena Trib. H Jefferson County 25% Complete

CONSTRUCTION PROJECTS STATUS

1998 was a busy year for the District's Design and Construction Program and saw us committing over $7.6 million to design and construction projects by year-end. Most of this funding has gone toward construction as well as initiation of several new design projects. Design and Construction currently has approximately 80 active projects in varying stages from design through construction.

The Drainageway A project in the City of Louisville came to a close at the end of 1998 with the completion of the detention pond improvements at Middle School Park and Lake Park. The added detention plus the outfall improvements installed in 1997 will eliminate a large area of downtown Louisville from the 100-year flood plain.

1998 marked the completion of the sixth and final phase of construction of the Upper Slaughterhouse Gulch Improvement Project. This project was initiated in 1985 with the City of Littleton and Arapahoe County and since that time the District has cooperated with Littleton and Arapahoe County in the construction of $7.6 million in drainageway improvements. Congratulations to Littleton and Arapahoe County for their perseverance in the completion of this much-needed improvement project.

Rehabilitation of two regional detention ponds was completed in 1998. The first, Tom Frost Reservoir in the City of Broomfield was completed this past year. In addition to the detention benefits, a pool area was created and the City was successful in obtaining a Fishing Is Fun grant from the Division of Wildlife to provide a fishing resource within the reservoir area. A second regional detention pond was rehabilitated in cooperation with the City of Thornton. Eastlake Reservoir No. 3 improvements were constructed which involved the installation of a new outlet works and spillway.

The first phase of construction of the Littles Creek improvement project was completed this past year which consisted of new crossings along Littles Creek at Delaware and Arapahoe Streets plus drainageway improvements. A second phase of construction is planned for 1999.

A number of storm sewer improvement projects were completed in 1998 in cooperation with the City and County of Denver, Cities of Brighton, Commerce City and Adams County.

Several new design projects were initiated in 1998. Some of the more interesting ones include Grange Hall Creek in the City of Northglenn, Niver Creek Tributary L in Thornton, Westerly Creek at Exposition Park in Aurora and Marston Lake North in the City and County of Denver.

Construction Photographs

Bear Canyon Creek in Boulder:
Click to enlarge...
Middle School detention pond on Drainageway A in Louisville:
Click to enlarge...
Tom Frost Reservoir in Broomfield:
Click to enlarge...
Littles Creek in Littleton:
Click to enlarge...

 

STATUS OF DISTRICT CONSTRUCTION PROJECTS

Project Jurisdiction(s)

Cost

Status
Cherry Cr. Drop at Iliff Arapahoe County

$475,000

Complete
Lone Tree Cr. Pond L-3 Arapahoe County

700,000

Complete
Dry Gulch at 14th and Lamar Lakewood

350,000

Complete
Bear Canyon Creek Boulder

1,000,000

Complete
Drainageway A Louisville

1,250,000

Complete
West Evans Ph. 2 Denver

500,000

Complete
Monaco/Eastman Outfall Denver

800,000

Complete
Tom Frost Reservoir Broomfield

570,000

Complete
Eastlake No. 3 Thornton

450,000

Complete
Kalcevic Gulch Ph. 1 Adams County

870,000

Complete
Greenwood Gulch Greenwood Village

1,800,000

Complete
Slaughterhouse Gulch Ph. VI Arapahoe County

1,100,000

Complete
Longs Way Tributary Parker, Douglas Co.

350,000

5% Complete
I-25/46th & Pecos Ph. IV and V Denver

600,000

10% Complete

Niver Creek Trib. M Federal Heights

200,000

50% Complete
Brighton North Outfall Brighton

1,000,000

95% Complete
Parker/Mexico Outfall Arapahoe County

800,000

25% Complete
West Evans Ph. III Denver

500,000

10% Complete
Lakewood Gulch – 10th Ave. Denver

700,000

10% Complete
20th & Meade Outfall Denver

800,000

10% Complete
Willow Creek Arapahoe County

550,000

40% Complete

              