STATUS OF DISTRICT DESIGN
PROJECTS
|
Project |
Participating Jurisdiction(s) |
Status |
Marston Lake N./Bear Cr. Park |
Denver |
Complete |
Ralston/Leyden Feasibility |
Arvada, Corps of Engineers |
On hold |
Van Bibber Final Design |
Arvada, Corps of Engineers |
Complete |
Little Dry Creek Phase C |
Westminster |
Complete |
Little Dry Creek RR Crossings |
Adams County |
Complete |
Massey Draw at Carr St. |
Jefferson County |
Complete |
Jewell Wetland Detention |
Aurora |
Complete |
Grange Hall Creek |
Northglenn |
80% Complete |
Lakewood Gulch - Perry St. |
Denver |
10% Complete |
Niver Creek Tributary L |
Thornton |
30% Complete |
Drainageway E |
Columbine Valley |
95% Complete |
Irondale 80th Ave. Outfall |
Adams County, Commerce City |
95% Complete |
Littles Creek |
Arapahoe County |
25% Complete |
Goose Creek Phase 3 |
Boulder |
25% Complete |
McKay Outfall |
Adams County |
50% Complete |
Pleasant View Trib. to Lena |
Jefferson County |
95% Complete |
Rangeview Gulch |
Littleton |
90% Complete |
Cottonwood Creek |
Arapahoe County |
40% Complete |
Westerly Cr. @ Expo Park |
Aurora |
40% Complete |
Lena Trib. H |
Jefferson County |
25% Complete |
CONSTRUCTION PROJECTS STATUS |
1998 was a busy year for the District's Design and Construction Program and saw us
committing over $7.6 million to design and construction projects by year-end. Most of this
funding has gone toward construction as well as initiation of several new design projects.
Design and Construction currently has approximately 80 active projects in varying stages
from design through construction.
The Drainageway A project in the City of Louisville came to a close at the end of 1998
with the completion of the detention pond improvements at Middle School Park and Lake
Park. The added detention plus the outfall improvements installed in 1997 will eliminate a
large area of downtown Louisville from the 100-year flood plain.
1998 marked the completion of the sixth and final phase of construction of the Upper
Slaughterhouse Gulch Improvement Project. This project was initiated in 1985 with the City
of Littleton and Arapahoe County and since that time the District has cooperated with
Littleton and Arapahoe County in the construction of $7.6 million in drainageway
improvements. Congratulations to Littleton and Arapahoe County for their perseverance in
the completion of this much-needed improvement project.
Rehabilitation of two regional detention ponds was completed in 1998. The first, Tom
Frost Reservoir in the City of Broomfield was completed this past year. In addition to the
detention benefits, a pool area was created and the City was successful in obtaining a
Fishing Is Fun grant from the Division of Wildlife to provide a fishing resource within
the reservoir area. A second regional detention pond was rehabilitated in cooperation with
the City of Thornton. Eastlake Reservoir No. 3 improvements were constructed which
involved the installation of a new outlet works and spillway.
The first phase of construction of the Littles Creek improvement project was completed
this past year which consisted of new crossings along Littles Creek at Delaware and
Arapahoe Streets plus drainageway improvements. A second phase of construction is planned
for 1999.
A number of storm sewer improvement projects were completed in 1998 in cooperation with
the City and County of Denver, Cities of Brighton, Commerce City and Adams County.
Several new design projects were initiated in 1998. Some of the more interesting ones
include Grange Hall Creek in the City of Northglenn, Niver Creek Tributary L in Thornton,
Westerly Creek at Exposition Park in Aurora and Marston Lake North in the City and County
of Denver.
Construction Photographs
Bear Canyon Creek in Boulder:
|
Middle School detention pond on Drainageway A in Louisville:
|
Tom Frost Reservoir in Broomfield:
|
Littles Creek in Littleton:
|
|
Project |
Jurisdiction(s) |
Cost |
Status |
Cherry Cr. Drop at Iliff |
Arapahoe County |
$475,000 |
Complete |
Lone Tree Cr. Pond L-3 |
Arapahoe County |
700,000 |
Complete |
Dry Gulch at 14th and Lamar |
Lakewood |
350,000 |
Complete |
Bear Canyon Creek |
Boulder |
1,000,000 |
Complete |
Drainageway A |
Louisville |
1,250,000 |
Complete |
West Evans Ph. 2 |
Denver |
500,000 |
Complete |
Monaco/Eastman Outfall |
Denver |
800,000 |
Complete |
Tom Frost Reservoir |
Broomfield |
570,000 |
Complete |
Eastlake No. 3 |
Thornton |
450,000 |
Complete |
Kalcevic Gulch Ph. 1 |
Adams County |
870,000 |
Complete |
Greenwood Gulch |
Greenwood Village |
1,800,000 |
Complete |
Slaughterhouse Gulch Ph. VI |
Arapahoe County |
1,100,000 |
Complete |
Longs Way Tributary |
Parker, Douglas Co. |
350,000 |
5% Complete |
I-25/46th & Pecos Ph. IV and V |
Denver |
600,000 |
10% Complete |
Niver Creek Trib. M |
Federal Heights |
200,000 |
50% Complete |
Brighton North Outfall |
Brighton |
1,000,000 |
95% Complete |
Parker/Mexico Outfall |
Arapahoe County |
800,000 |
25% Complete |
West Evans Ph. III |
Denver |
500,000 |
10% Complete |
Lakewood Gulch 10th Ave. |
Denver |
700,000 |
10% Complete |
20th & Meade Outfall |
Denver |
800,000 |
10% Complete |
Willow Creek |
Arapahoe County |
550,000 |
40% Complete |
[ Up ] [ Cover Story ] [ Activities & Links ] [ Tucker-Talk ] [ Flood Warning ] [ Floodplain Management ] [ Master Planning ] [ Construction ] [ Maintenance ] [ South Platte River ] [ River Restoration ] [ Tamarisk Infestations ] [ Bank Stabilization ] [ NPDES Permitting ] [ Drop Structure Design ] [ Other News ]