|
Design and Construction Program Notes
|
STATUS OF DISTRICT DESIGN PROJECTS |
||
Project |
Participating
Jurisdiction(s) |
Status |
North
Tributary of Massey Draw |
Jefferson
County |
Complete |
Lakewood
Gulch @ Welchester Park |
Jefferson
County |
Complete |
Drainageway
G |
Jefferson
County |
Complete |
Cottonwood
Creek |
Arapahoe
County |
Complete |
Happy
Canyon Creek |
Douglas
County |
Complete |
Brookridge/Grant
Outfall |
Arapahoe
County |
Complete |
Cherry
Crest West Outfall |
Arapahoe
County |
Complete |
Erie
Drainage |
Erie |
Complete |
Leyden
Dam |
Arvada |
Complete |
McKay
Outfall |
Adams
County |
95%
Complete |
Pinehurst
& Academy Park Tribs |
Denver |
95%
Complete |
Plaster
Reservoir Detention |
Broomfield |
90%
Complete |
South
Lakewood Gulch |
Lakewood |
50%
Complete |
Kalcevic
Reservoir |
Adams
County |
35%
Complete |
Lena
Gulch @ Mountain Side |
Jefferson
County |
30%
Complete |
Parker/Jewell
Outfall |
Arapahoe
County |
25%
Complete |
Arvada
Channel |
Arvada |
20%
Complete |
Little
Willow Creek |
Douglas
County |
10%
Complete |
Sand
Creek Stapleton to Toll Gate |
Aurora |
5% Complete |
Sulpher
Gulch |
Parker |
5% Complete |
The year 2001 saw us committing over $8 million to design and construction projects by year-end. Most of this funding has gone toward the construction of several new projects as well as the continuation of projects started in past years. One notable change to the Design and Construction Program was the addition of Ken MacKenzie as Project Engineer effective February of this year. After several years of trying to manage 80 to 90 projects each year, Paul and I are grateful for the assistance that Ken is now giving us. We are currently working toward dividing the District by county with Paul responsible for Douglas and Arapahoe Counties, Ken for Denver and Jefferson Counties and myself for Adams and Boulder Counties. We thought it advantageous to have local governments dealing with only one point of contact for capital projects.
STATUS OF DISTRICT CONSTRUCTION PROJECTS |
|||
Project |
Jurisdiction(s) |
Cost |
Status |
Westerly Creek @ Expo Park |
Aurora |
$3,400,000 |
Complete |
Meadowood Creek |
Aurora |
3,204,000 |
Complete |
Cherry Creek Drops |
Glendale |
700,000 |
Complete |
Grange Hall Creek Phase 2/3 |
Northglenn |
1,506,000 |
Complete |
Weaver Creek @ Simms |
Jefferson County |
1,020,000 |
Complete |
South Trib. Slaughterhouse Gulch |
Littleton |
837,000 |
Complete |
Twenty Mile Detention |
Parker |
795,000 |
Complete |
Lakewood Gulch @ Perry |
Denver |
1,136,900 |
Complete |
Big Dry Creek Trail |
Littleton,
Englewood |
715,000 |
Complete |
Virginia Village Outfall Phase 1 |
Denver |
1,230,000 |
Complete |
Valley Club Outfall |
Arapahoe County |
1,400,000 |
Complete |
Pleasantview Tributary |
Jefferson County |
281,000 |
Complete |
Shaw Heights Trib. Phase II |
Westminster |
638,000 |
Complete |
Goose Creek |
Boulder |
3,803,000 |
95% Complete |
Bear Creek Maintenance Access |
Morrison |
817,300 |
95% Complete |
Leyden Dam |
Arvada |
1,604,000 |
95% Complete |
Little Dry Creek RR Culverts |
Adams County |
3,200,000 |
95% Complete |
Niver Trib. M Outfall |
Federal Heights |
172,000 |
95% Complete |
Marcy Gulch |
Highlands Ranch |
1,800,000 |
90% Complete |
Lemon Gulch |
Douglas County |
815,000 |
90% Complete |
Cottonwood Creek |
ArapCo,
Greenwood |
1,360,200 |
85% Complete |
Dad Clark Gulch |
Highlands Ranch |
523,000 |
80% Complete |
Wonderland Creek |
Boulder |
575,000 |
80% Complete |
Indiana St. Outfall |
Lakewood |
950,000 |
75% Complete |
Virginia Village Phase II |
Denver |
789,000 |
50% Complete |
A number of unique projects were constructed this past year including some which had been many years in the planning and design process. The Little Dry Creek Railroad Culverts project in Adams County was completed this year. Design of this project was initiated in the early 1980s and it took several years of negotiations with the Burlington Northern Santa Fe Railroad before final agreement was reached in late 2000. Hats off to Adams County for their persistence in bringing this project to fruition. Adequate conveyance is now available to carry 100-year flows between Federal Boulevard and Clear Creek; and a much needed trail connection is now in place along Little Dry Creek from Arvada and Westminster to the Clear Creek trail corridor.
Acquisition and construction of improvements to Leyden Reservoir were also completed in 2001. This was a joint project with the Cities of Arvada and Westminster. Acquisition of the property and the commitment of funding for the improvements took a yeoman effort on the part of the City Managers of Arvada and Westminster, as well as the Jefferson County Administrator. The improvements consisted of construction of a 380-foot wide spillway over the top of the existing 40-foot high dam. The new spillway is capable of safely passing 75% of the Probable Maximum Flood. Unique to this project was the use of roller compacted concrete to construct the spillway. Leyden Dam will now fully detain the 100-year event cutting approximately 2,000 cfs from the previous master plan release of approximately 2,200 cfs. We are just now starting the Letter of Map Revision process for what we anticipate to be significant impacts to the downstream floodplain along Leyden and Ralston Creeks.
Looking upstream at the new Perry Street bridge along
|
Goose Creek form liner detail. |
Constructing a soil cement drop structure on Marcy Gulch. |
The third and final phase of Grange Hall Creek was completed this past year in the City of Northglenn. The uniqueness of this project was in the nineteen drop structures constructed along Grange Hall Creek and its North Tributary. These two and four foot drops were constructed of concrete utilizing a reinforced concrete substructure with a colored shotcrete covering. After application of the shotcrete, the finished surface was sculpted to give the appearance of a rock outcrop. These feaux rock structures have been getting considerable attention in the metropolitan area and we anticipate using them on other projects. The Grange Hall Creek Project received the Grand Award at this years Annual Conference of the Colorado Association of Stormwater and Floodplain Managers. Congratulations to the City of Northglenn and Muller Engineering for their fine work on this project.
Yet another phase of Goose Creek in the City of Boulder was completed this past year. Unique to this project was the use of a very intricate form liner, which gives the appearance of a rock wall. Coloration was added to the individual concrete rocks to enhance the appearance of the wall. The final phase of the Goose Creek channel improvements was bid by the City of Boulder in late 2001 and should be starting early in 2002. This will conclude a multi-year multi-phase project that was initiated in the mid-1980s. The resultant 100-year channel improvements will remove a number of properties from the floodplain.
The year 2002 looks to be very busy with funding identified in the 5-Year Capital Improvement Program for 40 new or existing projects.