Maintenance
Up

 

Maintenance Program Activities
by
Mark R. Hunter, P.E., Chief, Maintenance Program

Routine Maintenance

Through the routine maintenance program $687,600 was spent in 2001 for mowing and debris pickups.  This work was done on approximately 240 different sections of urban drainageways within the District boundaries.  This equates to a total of over 100 miles of drainageways in the Denver area on which we performed scheduled mowing and debris pickup maintenance.

Many of the more urban drainageways now receive four or five mowings and seven or eight debris pickups per year.  In the early 1980s the sole purpose of the routine program was to pick up large debris that could otherwise contribute to blockages and flooding problems.  These days urban drainageway corridors are prized as neighborhood amenities.  Along with that outlook comes the community desire for a level of drainageway maintenance that goes beyond our original flood control debris pickups.  Three or four debris pickups per year is now inadequate on the more urban drainageways that we maintain.

All of our routine work is done on structured schedules by private contractors.  We are not set up to carry out landscape maintenance, on-call work, or emergency services.  In the past we have participated with other agencies by splitting maintenance duties along drainageways through improved parks.  We have seldom been pleased with our performance in these areas.  Recognizing this, we will resume our initial policy of not providing mowing and debris pickup on irrigated drainageway corridors.

For the year 2001 we awarded eight separate contracts for routine work.  All eight contracts were awarded through a direct competitive bid process.  This was the first year all routine contracts were competitively bid.  Over the last four years we have been transitioning away from awarding routine contracts based on an internal review of contractor proposals and toward awarding them based on the competitive bid process.  For the year 2002 we will add a provision to the routine contracts that will allow us to negotiate contract renewals for 2003 if we are satisfied with the contractor's work.

Restoration Maintenance

In 2001 the restoration program completed $1,887,000 of work.  Restoration projects typically address isolated drainage problems where the solution involves small-scale construction.  Eighty-seven individual activities were completed during the year.  A major advantage of the restoration program is the ability to use it to react quickly to local drainage needs.

The topography in the Denver area is generally steep enough that stream erosion is a rapid and visible element of the hydrologic cycle.  When development occurs streams are often confined to inflexible corridors.  If the stream corridor is narrow little room is available for the common episodes of erosion.  A frequent method of controlling vertical stream erosion is to install drop structures to dissipate the energy.  A drop structure must be stout in order to withstand the erosive power of a stream.

To borrow a football cliché, only three things can happen to a drop structure and two of them are bad.  In the first case, drops can fail when water flows through, under, or around them due to an inadequate cutoff wall.  In the second case, they can be damaged when the structure itself is not robust enough to withstand and dissipate the stream's energy.  Only if all goes well with the design and construction will the drop structure provide years of stable and durable grade control.

Our restoration program repaired several drop structures that suffered the first type of failure.  The drop structures on Greenwood Gulch in Greenwood Village were built in 1998, but three of them were showing signs of water flowing around the sides of the structures.  These were originally built as low-flow drops with grouted boulders as the cutoff wall.  We repaired them by driving a ten-foot deep sheet pile wall on their upstream edge and grouting the connection from the sheet pile to the existing boulders.

Before

After

Harvard Gulch looking upstream from Madison Street.
Drop structure has failed--water going under drop.

New drop structure with concrete cutoff wall.

A drop structure of concrete rubble and grout had been in place for years on Harvard Gulch just upstream of Madison Street in Denver.  This facility had no cutoff wall and had been undermined by the stream.  Our approach was to trench and pour a concrete wall for the cutoff and to use grouted boulders for the sloping face of the structure.

It is common to have utility lines cross streams.  Many of them end up with concrete encasements to protect the utility from the stream.  On Massey Draw, North Tributary in Jefferson County the stream eroded both under and around one end of a sewer line encasement.  With the financial assistance of the sewer district we poured a concrete cutoff wall and placed grouted boulders for the drop structure face.

We also repaired several facilities that suffered from the second type of drop structure damage.  A Capital Program project from the 1970s on Sanderson Gulch in west Denver included drop structures made of gabion baskets.  The high bed load of sediment and vandalism combined to limit the service life of the gabions.  The gabion drop on the east side of Federal Boulevard had been repaired in the past with sprayed-on concrete, but that was now deteriorating.  We replaced that structure with a trenched and poured concrete cutoff wall with grouted boulders for the sloping face.  We will continue replacing the old drop structures on Sanderson Gulch as funds are available.

Boulder Creek 9/27/01
Boulder Creek in the City of Boulder - restored drop structure.

Just south of C-470 in Douglas County Willow Creek flows through an undeveloped area.  Similarly, in Brighton, Line A, also called North Urban Channel, discharges to the South Platte River after flowing through a rural area.  The structures on both these creeks shared a similar history in that they suffered from increased flows due to upstream development and the downstream channel was degrading resulting in undermining of the facilities.  For both these structures we drove sheet pile to establish the cutoff wall and installed grouted boulders to create the face of the drop.  We realize that since there is no grade control downstream of these structures they will still be vulnerable to vertical erosion in the downstream channel.

Stream-rounded boulders were used over the years by the City of Boulder to establish a dozen drop structures on Boulder Creek.  These drops are two to three feet tall and have no concrete and no cutoff wall.  The original boulders were locked into an arch shape through careful placement, but, eventually, in the cobble-bedded stream some of the rounded boulders became displaced.  We imported some angular boulders and re-established an arched grade wall bedded in the cobbles.  The rounded boulders were then placed downstream of the grade wall to give a sloping face to the structure.

Rehabilitation Maintenance

Twenty-four projects were at various stages of design or construction during 2001. Those projects are listed in the accompanying table titled STATUS OF MAINTENANCE REHABILITATION PROJECTS. Rehabilitation projects usually take the form of consultant-designed repairs that are intended to address severe problems that have occurred on a previously improved urban drainageway. By the end of 2001 the District will have spent about $2,559,300 on rehabilitative design and construction for the year. A few of the unique projects are discussed below.

Niver Creek Tributary M - looking downstream from Huron Street. Severe channel degradation has been offset with urban debris. Construction begins January 2002.

We are always doing something on Cherry Creek.  In southeast Denver where the Highline Canal crosses the creek there is a massive 12 foot tall drop structure composed of dumped concrete rubble.  As the creek bed downstream has degraded the structure has evolved into a drop that protects the Highline Canal siphon that crosses under Cherry Creek.  Erosion has now exposed the siphon and the rubble appears inadequate to resist a major flood event.  Several regional and local governments are participating with us in rebuilding this substantial structure including trail and park improvements for the large open space area.

Niver detention pond is a large regional facility located west of I-25 at 88th Avenue.  Tributary M to Niver Creek joins Niver Creek just upstream of the dam.  The dam provides some grade control, but by the time Tributary M reaches Huron Street the erosion is severe with 12 to 15 foot tall vertical banks and a headcut undermining the Huron Street culvert.  Our project will include five drop structures and extensive bank reshaping.

One of this year's projects includes the elimination of an 18-inch diameter trickle flow/underdrain pipe.  The East Toll Gate Tributary in Aurora has several grouted rock drop structures with deep stilling basins that drain into the 18-inch trickle flow pipe.  The pipe is damaged or plugged in several areas.  The drops are deteriorated and have become a safety problem because of the deep stilling basins.  Rebuilding the drop structures and regrading the channel will allow all runoff to flow on the surface through the improved corridor.  Aurora plans to upgrade the site to an irrigated bluegrass park.

Harvard Gulch Harvard Gulch

DeBoer Park low flow channel before and after.

The City of Denver also had a channel with a troublesome underdrain pipe.  Harvard Gulch flows through DeBoer Park in south Denver.  The underdrain was connected to multiple surface inlets with the intent of keeping the area dry during low flow periods.  The thin slope-paved concrete of the trickle channel through the park had become displaced and broken-up to the extent that the trickle flows went under or around the inlets and never made it to the underdrain pipe.  With the coordination of Denver Parks the five-foot wide concrete trickle channel was replaced with a boulder-edged low flow channel that varies from 10 to 15 feet wide.

Lilley Gulch

Lilley Gulch looking downstream toward Wadsworth Blvd. 
Note the undermined pedestrian trail and general channel
degradation.  Construction begins January 2002.

With the acquisition, by Foothills Park District, of a parcel of land west of Wadsworth Boulevard a final link was made in the Lilley Gulch corridor in Jefferson County.  The additional public land allowed us to incorporate a re-aligned trail, streambank protection, and several areas of wetlands.  Four drop structures will also be built to control the grade through this new open space park.


Up ] Cover Story ] Tucker Talk ] Floodplain Mngmt ] Flood Warning ] CoCo RaHS ] Master Planning ] Stormwater ] Construction ] [ Maintenance ] Maint Eligibility ] South Platte River ] Activities ] News Briefs ]

Print Version