Cover Story
Up

Printer-friendly version

E-470 Major Drainageway Design Enhanced Through Regional Cooperation

By
Ken Mauro, P.E., Design Manager, E-470 Public Highway Authority
Doug Weber, P.E., Senior Project Manager, Washington Group International
David Mallory, P.E., Senior Project Engineer, Floodplain Management Program

E-470 is the eastern one-half of the Denver Metropolitan Area's beltway system. The total length of the E-470 Tollway is approximately 48 miles long, extending from a south connection with I-25 at C-470 to a north connection with I-25 at approximately East 158th Avenue. The initial configuration for the tollway is four lanes with a grassed median. The limited access roadway has interchanges at numerous intersecting major arterial roads and highways. The ultimate configuration includes eight lanes and potential for light rail or other HOV use in the median. Construction was completed in four major segments over a 12-year period beginning in 1991.

The Public Highway Authority (PHA) and a team of consulting engineers and environmental planners commenced planning and preliminary routing years earlier. Early in the process, the PHA and the District endeavored to cooperate on regional drainageway planning and implementation. The strategy was to locate regional flood attenuation facilities, or detention ponds upstream of roadway crossings, which could be sized for a lower discharge rate. This strategy worked well in implementing District master plans, reducing highway construction costs, and fostering sound floodplain management policies. The various local governments that make up the E-470 Public Highway Authority all benefited from these regional drainageway planning efforts. Quincy Pond on West Toll Gate Creek, Gun Club Road Ponds on Tributary T to First Creek and the Second Creek Pond at Denver International Airport (DIA) are all examples of cooperative efforts completed during the first three segments of E-470 that resulted in regional drainageway benefits.

The fourth and final segment of E-470 is approximately 12 miles long and traverses through portions of Commerce City, Brighton, Thornton, and unincorporated Adams County from East 120th Avenue to I-25. This segment of E-470 crosses the South Platte River, Big Dry, Todd, Second and Third Creeks, and several tributaries. The design team for this segment was a joint venture of Washington Group International and Parsons Transportation Group. The construction group was a joint venture of Washington Group International and Kiewit Construction Company. Staffs from PHA, the design/build group and several local, regional and federal agencies worked on solving the various design problems. Final design plans for Sack Creek, Short Run, Second Creek, Fox Run (a tributary in Direct Flow Area 0053) and Third Creek all involved extensive coordination and cooperation in order to provide adequate roadway design and at the same time implement portions of District master plans. The best example of design team/agency cooperation is in the Third Creek drainageway area.

The Third Creek basin originates upstream from Denver International Airport (DIA) and flows northwesterly to the confluence with the South Platte River, draining a total of 32 square miles. Adams County and the Cities of Commerce City and Brighton are all affected by Third Creek. Several irrigation canals traverse the basin and several wetland areas are adjacent to the creek. The basin below DIA is presently rural in nature; however rapid development is expected as a result of the E-470 and DIA projects. Third Creek has been studied extensively beginning with a Flood Hazard Area Delineation (FHAD) study prepared by the District in 1976. The District subsequently published an Outfall Systems Planning (OSP) Study in 1990. The Federal Emergency Management Agency (FEMA) published a Zone A floodplain based on the FHAD study. The influence of DIA was identified in a hydrologic update, "Third Creek Implementation Plan", prepared by the District in October of 2000. The FHAD identified a 100-year discharge of approximately 6,000 cfs through the project reach. The OSP identified a 100-year discharge of 10,000 cfs without detention and 4,600 cfs with detention at Interstate Highway 76 (I-76). The attenuated flows include the effects of two proposed detention ponds within the study reach, in addition to DIA detention facilities.

Third Creek and E-470 vicinity

Looking downstream along Third Creek north of 120th Ave. Looking northwest along E-470 with the 120th Ave. detention pond on the right.
Looking south from Third Creek toward the Buffalo Run detention site.

Because of environmentally sensitive vegetation within the basin between Buckley Road and I-76, the E-470 alignment was located near or on the thalweg of Third Creek through this reach. Placing a roadway on embankment within the floodplain produced significant impacts requiring careful mitigation. The Third Creek thalweg had to be relocated through much of the project reach. Buffalo Run, a 2.4 square mile tributary, crosses E-470 immediately upstream of its confluence with Third Creek west of Buckley Road. The O'Brian Canal crosses Buffalo Run, Third Creek and E-470. The Burlington Canal and Buffalo Run share a combined E-470 crossing structure.

The problem was to place the E-470 highway embankment along Third Creek with minimal impact to the wetlands vegetation and 100-year floodplain. Early conceptual planning ruled out channelization as envisioned in the OSP due to environmental and groundwater concerns. A plan was developed that utilized elements from the original OSP, modified to accommodate E-470. The plan included using borrow pits resulting from roadway embankment excavations for regional detention ponds. The first pit, located south of East 120th Avenue was designed as a 267 acre-foot online peak shaving detention pond. This pond replicates OSP pond number 261 in terms of general location and function. The OSP identified a second regional detention pond offline from Third Creek, upstream of I-76 to further reduce 100-year peaks discharges to the northwest. That site was needed for wetlands mitigation. The design team identified a borrow pit south of the O'Brian Canal and along Buffalo Run as a potential regional detention pond replacement site. Preliminary design was performed to insure that the borrow pit size was adequate to reduce downstream 100-year peak discharges on Third Creek to approximately the OSP values. Additional analysis and design were performed to identify a future pond outlet system beneath the O'Brian Canal and discharge channel beneath the E-470 mainline bridges. Commerce City, the District and several development groups subsequently completed a separate Buffalo Run master plan effort. The Third Creek low flow channel between East 120th Avenue and I-76 and beyond to Sable Boulevard (State Highway 2) was relocated and widened to minimize impacts to the floodplain. The E-470 design effort was coordinated with CDOT's I-76/Third Creek bridge replacement project.

Coordination between the design team, FEMA and the District was required to update floodplain hydrology for Third Creek. The District provided revised floodplain hydrology, based on existing basin conditions in accordance with FEMA criteria. Floodplain hydrology in this case differed from design discharges, which were based on developed basin conditions. The 100-year discharge at I-76 was estimated at 3,500 cfs while the design discharge at this same location was estimated to be 4,800 cfs. Both a Conditional Letter of Map Revision and final Letter of Map Revision were prepared for the project reach. The District completed the technical review on behalf of FEMA under the Cooperative Technical Partners program.

Because existing wetlands along Third Creek were impacted, a mitigation plan was required. Cooperation with Army Corps of Engineers, Environmental Protection Agency, Brighton, and Adams County, was required to provide an acceptable mitigation plan. The plan included designing the relocated low flow channel as a wetland bottom facility and constructing four wetland mitigation sites adjacent to the creek. The mitigation plan was approved by local jurisdictions and federal agencies.

Cooperation between E-470 PHA--providing the land, the Contractor--completing the pond excavation, CDOT--providing approval of revised hydrology at I-76 and Sable Boulevard, and the District and Commerce City--accepting the borrow pit for use as a future regional detention facility was required to make this plan acceptable. The hard work and cooperative spirit of the stakeholders was essential in developing, reviewing, and approving the proposed Third Creek improvement plans. Time is money on design/build projects. The coordinated effort of the stakeholders allowed construction of the fourth segment of E-470 Tollway to be completed ahead of schedule. At the same time two additional master planned regional detention facilities were constructed and are in place ahead of the development that is expected to follow the highway.


[ Home ] [ Cover Story ] Tucker Talk ] Awards ] Floodplain Management ] Maintenance Eligibility ] Flood Warning ] Master Planning ] Stormwater Permits ] Atmospheric Dust ] South Platte River ] Protecting Trees ] Design and Construction ] Maintenance ] News Briefs ] Professional Activities ]